Mmamabula coal exports unviable

Location of African Energy's three coal resources in the central district
Location of African Energy's three coal resources in the central district

A pre-feasibility study at African Energy’s Mmamabula West coal project has cast doubts about the viability of exporting coal from the proposed mine at prevailing coal prices.

The results of the study found that it will take either a fall in rail tariffs or increase in coal price to make the coalmine project sustainable and profitable.

The underground operation would have a run-of-mine output of some 4.4-million tonnes a year, and would require a capital investment of $113-million (P994 million) for an owner-operated mine and coal handling and processing plant over a mine-life of 20-years.

Editor's Comment
Inspect the voters' roll!

The recent disclosure by the IEC that 2,513 registrations have been turned down due to various irregularities should prompt all Batswana to meticulously review the voters' rolls and address concerns about rejected registrations.The disparities flagged by the IEC are troubling and emphasise the significance of rigorous voter registration processes.Out of the rejected registrations, 29 individuals were disqualified due to non-existent Omang...

Have a Story? Send Us a tip
arrow up