Mmegi

Tlou nears grid link-up

Burning bright: Tlou has fully tested its flaring rates and other capacities
Burning bright: Tlou has fully tested its flaring rates and other capacities

Tlou Energy, the country’s most advanced Coal Bed Methane developer, says construction of its delayed Lesedi substation is now at 90 percent, with completion necessary to achieve grid access for gas fired power for the first time in the country’s history.

In a quarterly update released this week, Tlou directors said in the third quarter, key subcontractors had been identified to finalise the work and the remaining items needed two to three months. The directors said while initially expected to have been completed in 2025, work on the substation had been delayed by funding.

The aim now is to complete it so that both gas-fired and solar power can flow through to the national grid. Tlou has plans to develop a five-megawatt solar plant at its licence area in the Central District, with expectations to expand this to 20MW, essentially building a hybrid energy project.

Tlou has a Power Purchase Agreement (PPA) with the Botswana Power Corporation to provide 10MW from the Lesedi project into the national grid. The company has plans to raise its production to a 25MW target and beyond that, 100MW.


Editor's Comment
DIS must correct costly stalemate

More than P8.1 million has already been spent, yet there appears to be no lasting solution in sight. This is not simply a dispute between the DIS and a group of officers. It is a matter of public accountability. Every pula spent by government comes from taxpayers who expect public funds to be used wisely and responsibly, especially during economic hardships faced by many.The officers exercised their constitutional right to seek justice through...

Have a Story? Send Us a tip
arrow up