Race Against Time To Complete NWTG

BPC Transmission line 2. PIC: MORERI SEJAKGOMO
BPC Transmission line 2. PIC: MORERI SEJAKGOMO

The Botswana Power Corporation (BPC) is in a race against time to reach set targets, but seems to be falling short of meeting the goal to finish the North West Transmission Grid Commission (NWTGC) project on schedule.

The NWTGC project’s progress as at July 2019 was at 73% against the targeted 86%.

However, Project Services manager, George Moeti there has revealed recovery plans in place to catch up on lost time.

Editor's Comment
Human rights are sacred

It highlights the need to protect rights such as access to clean water, education, healthcare and freedom of expression.President Duma Boko, rightly honours past interventions from securing a dignified burial for Gaoberekwe Pitseng in the CKGR to promoting linguistic inclusion. Yet, they also expose a critical truth, that a nation cannot sustainably protect its people through ad hoc acts of compassion alone.It is time for both government and the...

Have a Story? Send Us a tip
arrow up