Race Against Time To Complete NWTG

BPC Transmission line 2. PIC: MORERI SEJAKGOMO
BPC Transmission line 2. PIC: MORERI SEJAKGOMO

The Botswana Power Corporation (BPC) is in a race against time to reach set targets, but seems to be falling short of meeting the goal to finish the North West Transmission Grid Commission (NWTGC) project on schedule.

The NWTGC project’s progress as at July 2019 was at 73% against the targeted 86%.

However, Project Services manager, George Moeti there has revealed recovery plans in place to catch up on lost time.

Editor's Comment
CoA brings sanity to DIS/DCEC long-standing feud

This decision follows the raiding of the office of the former Director General of the DCEC, Tymon Katlholo early 2022 and his staff officer by the DIS operatives who reportedly took files that they had targeted.After all back and forth arguments, the CoA has set the record straight giving an invaluable lesson to the DIS that it was no super security organ and it does not have any powers to cogently supervise other security organs including the...

Have a Story? Send Us a tip
arrow up