Cautious optimism as Morupule B undergoes rebirth

Morupule
Morupule

After a period of haggling over terms, a major overhaul has kicked off at Morupule B to get the 600MW plant fully functional for the first time in its seven-year life. The Botswana Power Corporation is confident lessons have been learnt. Cynics are shaking their heads Staff Writer, MBONGENI MGUNI reports

PALAPYE: The list of experts the Botswana Power Corporation (BPC) has brought in for the $120 million overhaul of Morupule B is extensive. It’s an army of experts charged with one mission: ensuring the mistakes of before are not repeated in the overhaul.

According to available documents, Morupule B’s failure to launch after its completion in 2012 was because of design, construction and quality issues in key components at the four units.

Editor's Comment
Watch your tongue Mr President

While his leadership has brought about significant progress and development, it is imperative that he exercises greater caution in his choice of words, particularly when addressing sensitive matters.One of the primary concerns is the potential impact of his remarks on Botswana’s relationship with De Beers, the diamond mining giant that plays a crucial role in the nation’s economy.The partnership between Botswana and De Beers has been mutually...

Have a Story? Send Us a tip
arrow up