Orange Data Centre Schedule Three Percent Ahead

Orange Botswana head technical director Gobe Mbayi
Orange Botswana head technical director Gobe Mbayi

Orange Botswana Data Centre project is making smooth progress, as it is three percent ahead of schedule.

The data centre project is at 27% completion and it is expected to be complete by end of October this year.

The data centre is said to cover 81% of the population with 2G technology, 62% of the population with 3G technology and 45% of the population with 4G technology offering greater levels of security, flexibility and access to data and information around the world.

Editor's Comment
Women in Politics caucus NGO, a welcome development

In the 2014 General Election, women who stood for parliamentary elections were a mere 17 out of a total of 192 aspirants, and sadly the number dropped to 11 out of 210 parliamentary aspirants in the 2019 General Election. Hopefully, registration of the Women in Politics Caucus will give women the necessary support to join politics. While things were slowly improving, women for a long time were at the receiving end as compared to their male...

Have a Story? Send Us a tip
arrow up