Orange Data Centre Schedule Three Percent Ahead

Orange Botswana head technical director Gobe Mbayi
Orange Botswana head technical director Gobe Mbayi

Orange Botswana Data Centre project is making smooth progress, as it is three percent ahead of schedule.

The data centre project is at 27% completion and it is expected to be complete by end of October this year.

The data centre is said to cover 81% of the population with 2G technology, 62% of the population with 3G technology and 45% of the population with 4G technology offering greater levels of security, flexibility and access to data and information around the world.

Editor's Comment
Keep your mask close

Wearing of masks behind closed doors has been mandatory following the government’s August decision that the public was freed from masking in outdoor spaces.According to a press statement from the ministry, all other remaining COVID-19 protocols such as social distancing in schools and requirements for vaccination or PCR tests at ports of entry have also been relaxed.Statistics still show that hundreds still die daily due to the pandemic around...

Have a Story? Send Us a tip
arrow up