More delays in Dikgatlhong Dam pipeline
Friday, June 22, 2012
The pipeline contract commenced last October and is slated for completion in October 2013.
The contractor, China State Construction and Engineering Corporation in a joint venture partnership with Excavator Hire, has already done 14 percent of the work instead of the expected 31 percent.
‘A man’s country is not a certain area of land, of mountains, rivers, and woods, but it is a principle and patriotism is loyalty to that principle’.- George William CurtisAccording to the report carried in this publication, the fraudsters operating the so-called “dark fleet” have selected Botswana’s flag as their cover of choice. This is a direct assault on our country’s most valuable asset, the good name.For decades, Botswana has...