Maun Copper Project Costs Rise To P1 Billion

The costs of Discovery Metals Limited (DML)'s Boseto Copper Project, have risen to US$150 million (P1.02 billion) on the back of increased contingency for price changes in capital components.

With resources of 60.4 million tonnes of copper, DML plans to open Botswana's largest copper mine in 2012, producing 25 000 tonnes of the base metal annually. The Maun-based project will also pump out 700 000 ounces of silver annually.

Last week preliminary findings from the ongoing Bankable Feasibility Study (BFS), showed that capital costs for Boseto have increased from the US$131 million (P895 million) estimated last year, on the need for additional contingency for price changes related to capital components.

Editor's Comment
Stakeholders must step up veggie supply

The Ministry of Agriculture, local producers, retailers, and industry associations must work together to overcome the obstacles hindering vegetable production and distribution.This collaborative approach is essential to improve the availability, quality, and affordability of vegetables in the market.Firstly, the Ministry of Agriculture should provide support and guidance to local farmers to enhance their productivity and efficiency. This could...

Have a Story? Send Us a tip
arrow up