Mosienyane and Partners International Consultants were engaged at a sum of over P2 million and the project that started in May 2012 was supposed to be completed in March 2013.
During the delivery of the Urban Development Plan (UDC) report, Economic Planner Ezekiel Joel said the project was 60 percent behind schedule.
While it is widely acknowledged that Khama holds the title of Kgosi, the government’s failure to properly gazette his recognition has raised serious concerns about adherence to legal procedures and the credibility of traditional leadership. (See a story elsewhere in this newspaper.) Recent court documents by the Minister for Local Government and Rural Development, Kgotla Autlwetse, shed light on the intricacies of Khama’s recognition process....