Khato cut cost of multimillion pula project

Critics blame the contractor for the ballooning of the project's budget
Critics blame the contractor for the ballooning of the project's budget

Documents perused by Mmegi have revealed that contrary to perceptions that the winning bidder, Khato Civils were responsible for the P900 million project cost hike that was recently put before Cabinet, and later surfaced in Parliament, the amount of cost estimates was done by the parent Ministry and Water Utilities Corporation’ (WUC).

It was also tabled before Cabinet way before the tender award was announced, the documents revealed.

The documents also established that when the award of the tender was announced, Khato’s winning bid was put at P781 million or USD 65 million, while the Ministry’s own project estimate later surfaced to be P900 million. Critics questioned the price hike and blamed the contractor for the ballooning of the project budget.

Editor's Comment
GCC should fix the Gabs water flow mess

The sight of submerged yards and closed roads is an inconvenience and a clear sign that the capital’s water passages pose a problem to residents. With more rain forecast, this is not a time for panic, as Gaborone City Council (GCC) Mayor Oarabile Motlaleng rightly urges, but it is most certainly a time for urgent, collective action.His appeal for calm must be matched by a firm commitment from both the GCC authorities and every single resident....

Have a Story? Send Us a tip
arrow up