Grandstand roof ommision angers FCC councillors
Tuesday, May 24, 2011
The remedial measures' report states that the Grandstand roof has been omitted in order to bring the project to practical completion. It also states that the contractor was slow to meet resource constraints and resolution is reported to be feeble in that area. Work movement was also reported to be slow.
The councillors are not amused that while money has already been spent the project is to be handed over in its incomplete state. The overall progress of the stadium is currently at 89 percent and the amount certified to date is P135,397,551.56.
It underscores the indispensable role women play in our society, particularly in building strong households and nurturing families. The recognition of women as the bedrock of our communities is not just a sentiment; it's a call to action for all women to stand together and support each other in their endeavours.The society's aim to instil essential principles and knowledge for national development is crucial. By providing a platform for...