‘Conflicted’ PS accused of delaying Kanye sanitation project
Friday, June 13, 2025 | 140 Views |
Khumotaka. PIC BW PARLIAMENT
The Kanye sanitation project made headlines recently when it was revealed that the project, initially set at P724.96 million, has drastically exceeded its budget, with costs ballooning to P3.4 billion. The project comprises a 480-kilometer pipeline, 11 pump stations, and wastewater treatment works. It was originally scheduled to run from October 2017 to October 2019, but has since been extended to July 2025.
Apart from the rocky conditions that come with the topographical terrain in Kanye, the delay has been blamed on some landowners in the village who are refusing to give contractors access to their homes. Fingers now point at Khumotaka, who is accused of being insincere and conflicted in the matter. Khumotaka recently informed the Public Accounts Committee (PAC) that the DCEC is investigating the project cost overrun, involving engineers accused of professional malpractice.
With his theme of 'Delivering on Our Promise, One Step at a Time', he sought to project an image of a focused, determined leader building a new ‘Rome’. Sadly, parts of his speech were not about laying bricks, but about settling old scores.It is deeply worrying that a head of government would use such a pivotal national address to launch another bitter broadside against the media and his political detractors. His portrayal of the...