Lucara's diamond mine on course for commissioning

Construction of Lucara's AK6 diamond mine is over 60 percent complete and the project is on course for commissioning in the fourth quarter of this year, the company says.

In a project update, Lucara says as at the end of May, there were over 400 construction crew members on site and a total of 326,000 hours worked. "With the overall project execution at 64 percent, the project remains on target for process plant commissioning to commence in the fourth quarter of this year," the company says in a statement.

"Engineering is now 91 percent complete, procurement is at 81 percent, fabrication and delivery at 55 percent, and construction at 39 percent complete. The project capital expenditure is also trending in line with the Feasibility Study estimate of $120 million."

Editor's Comment
Women unite for progress

It underscores the indispensable role women play in our society, particularly in building strong households and nurturing families. The recognition of women as the bedrock of our communities is not just a sentiment; it's a call to action for all women to stand together and support each other in their endeavours.The society's aim to instil essential principles and knowledge for national development is crucial. By providing a platform for...

Have a Story? Send Us a tip
arrow up