Govt admits bungling in SSKIA tender

No Image

The Permanent Secretary in the Ministry of Infrastructure, Science and Technology has said government chose an inappropriate procurement strategy and took too much risk in the awarding of the tender for the expansion of the Sir Seretse Khama International Airport (SSKIA).

Speaking before the Public Accounts Committee (PAC) this week, Kagiso Mokotedi said that because of desperation to finish expansion of the airport before the June 2012 FIFA World Cup hosted by South Africa, there were anomalies in the way the tender was awarded.

The tender was awarded to Sinohydro in April 2008 at an initial cost of P433 million that later ballooned to P555 million."As government, we were too much in a hurry to compete the project before the start of the World Cup. We did not choose the appropriate procurement strategy and as a result, there were uncertainties right from the onset of the expansion project.

Editor's Comment
Stakeholders must step up veggie supply

The Ministry of Agriculture, local producers, retailers, and industry associations must work together to overcome the obstacles hindering vegetable production and distribution.This collaborative approach is essential to improve the availability, quality, and affordability of vegetables in the market.Firstly, the Ministry of Agriculture should provide support and guidance to local farmers to enhance their productivity and efficiency. This could...

Have a Story? Send Us a tip
arrow up