Paid millions for failure

The Department of Local Government Finance and Procurement Services Gaborone has been found to be rewarding failure with multi-millions.

The latest Auditor General's reports finds that a contract for the manufacture and supply of milk (1,076,520 cartons), with scheduled deliveries monthly to seven depots failed to perform but nevertheless continued to be rewarded with more lucrative tenders.

The audit finds that the initial tender covered the period from April 2010 to March 2011. However, when the supplier failed to meet  the full compliment of scheduled deliveries resulting in depots being short-supplied for the period of April to December 2010 and other months, the contractor was given an extention to August 2011.

Editor's Comment
Women unite for progress

It underscores the indispensable role women play in our society, particularly in building strong households and nurturing families. The recognition of women as the bedrock of our communities is not just a sentiment; it's a call to action for all women to stand together and support each other in their endeavours.The society's aim to instil essential principles and knowledge for national development is crucial. By providing a platform for...

Have a Story? Send Us a tip
arrow up