Debswana axes P15.7bn contract to deepen Jwaneng Mine
Friday, January 15, 2021
In a statement on Monday, Debswana said the termination of the contract is with effect from Jan 4 and the contractor, Majwe Mining, had been given a 90-day notice period.
“The Cut 9 operation will transition to an owner-mining operation with some of the key services and resources, such as labour, being provided by contractors/service providers to Jwaneng Mine,” Debswana’s head of corporate affairs, Rachel Mothibatsela said.
The recent disclosure by the IEC that 2,513 registrations have been turned down due to various irregularities should prompt all Batswana to meticulously review the voters' rolls and address concerns about rejected registrations.The disparities flagged by the IEC are troubling and emphasise the significance of rigorous voter registration processes.Out of the rejected registrations, 29 individuals were disqualified due to non-existent Omang...