Morupule B shines after 10-year storm

Coming soon: Morupule B’s overhaul is due complete by January 2025 PIC: MBONGENI MGUNI
Coming soon: Morupule B’s overhaul is due complete by January 2025 PIC: MBONGENI MGUNI

After numerous breakdowns and billions of Pula in costs to the economy, the Morupule B power station appears to be on the road to full functionality, ten torturous years after it was first “completed”. Staff Writer, MBONGENI MGUNI reports on one of the country’s single most expensive investments

Three years ago, the Botswana Power Corporation (BPC) invited media to its troubled 600MW Morupule B power station outside Palapye for the installation of a major component.

The exercise was said to demonstrate the start of extensive remedial works expected to cost $120 million (P1.2 billion at 2019 rates).

Editor's Comment
Ruling party should tread carefully on cadre deployment

But on the particularly sensitive question of cadre deployment, the BNF must tread very carefully.The issue deserves robust debate, not ideological enthusiasm. Recent public comments from the BNF leadership are reassuring: the party has said that government positions should be based on merit and competence rather than party membership, and that it does not have a specific cadre-deployment policy.That principle should remain firmly at the centre...

Have a Story? Send Us a tip
arrow up