Morupule B shines after 10-year storm

Coming soon: Morupule B’s overhaul is due complete by January 2025 PIC: MBONGENI MGUNI
Coming soon: Morupule B’s overhaul is due complete by January 2025 PIC: MBONGENI MGUNI

After numerous breakdowns and billions of Pula in costs to the economy, the Morupule B power station appears to be on the road to full functionality, ten torturous years after it was first “completed”. Staff Writer, MBONGENI MGUNI reports on one of the country’s single most expensive investments

Three years ago, the Botswana Power Corporation (BPC) invited media to its troubled 600MW Morupule B power station outside Palapye for the installation of a major component.

The exercise was said to demonstrate the start of extensive remedial works expected to cost $120 million (P1.2 billion at 2019 rates).

Editor's Comment
Our digital safety is in our hands

That sounds like good news. But the report also warns that this may simply be because our digital economy is still young, not because we are safe. As more people shop, bank and pay online, criminals will follow.We Batswana do not need a report to tell us that danger is real. Many of us have heard of or fallen victim to KYC scams. A caller impersonates your bank or mobile money provider. They say they need to “verify” your account. They ask...

Have a Story? Send Us a tip
arrow up