Tlou to complete 10MW project in 2023 third-quarter
Wednesday, March 15, 2023 | 980 Views |
Gilby
The 100km transmission line runs from Nyamakatse to Botswana Power Corporation’s (BPC) substation in Serowe. Commenting on the group’s half-year financial results for the year ended December 31, 2022, Managing Director Anthony Gilby said construction of the transmission line is being done by Zismo Engineering Pty Ltd (Zismo) with February end progress at approximately 50%.
“The company is working on bringing the Lesedi 10MW GTP project into production as quickly as possible and, subject to available funding, Tlou plans to rapidly expand to 25MW and beyond,” he said.
That a single private law firm pocketed P6.5 million for just four cases, out of a total P11.1 million paid for 25 matters, reeks of a system that was not merely disorganised but open to abuse.Bayford has taken a welcome first step by telling the Public Accounts Committee the truth. Now he must act decisively to ensure it never happens again and that any money lost to wrongdoing is recovered.The figures are staggering. Whilst ordinary Batswana...