PPADB approves P704m Kanye water tender
Thursday, July 03, 2014
According to the chief water engineer at Water Affairs department, Gabalemogwe Moanakwena, the project is expected to commence beginning of August and be completed in January 2017.
“The contractor’s offer was accepted on 23 June 2014 and they accepted our proposal on 24 June 2014. Commencement of the actual works is between the above 28 days and 42 days. This translates to 04 August 2014,” said Moanakwena.
According to both the acting director of Veterinary Services, Kobedi Segale and acting Lands and Agriculture minister, Edwin Dikoloti, the virus currently raging through the North-East mostly likely first entered the country during the festive season.From the “unprecedented” number of cases picked in testing last week, it is likely that cattle and other livestock could have been infected last year, without being reported.Animal health...