Government retrieved the penalty from the project’s initial P433 million contract sum in November 2012 as a contract default penalty. This followed the termination of Sinohydro’s Sir Seretse Khama International Airport (SSKIA) contract in July 2012 for “ failure to complete the expansion of the airport within stipulated time frames and cost estimates”.
In a matter heard by Justice Michael Leburu last week, Sinohdryo is seeking the High Court to order government to pay back the P43 million, and deposit the monies into a mutually held account as directed by the Dispute Adjudication Board(DAB).
The recent disclosure by the IEC that 2,513 registrations have been turned down due to various irregularities should prompt all Batswana to meticulously review the voters' rolls and address concerns about rejected registrations.The disparities flagged by the IEC are troubling and emphasise the significance of rigorous voter registration processes.Out of the rejected registrations, 29 individuals were disqualified due to non-existent Omang...