Road projects hit brick wall

Construction of Moshopa-Manyana Road. PIC MORERI SEJAKGOMO
 
Construction of Moshopa-Manyana Road. PIC MORERI SEJAKGOMO

The 2026 Strategic Impact Report on National Transformation has exposed serious implementation challenges confronting President Duma Boko’s administration. The report, which was released recently, lays bare the extent of the delays plaguing the country’s road construction programme, with some projects recording less than half of their anticipated progress. In a candid admission buried in the 96-page report, government acknowledges that contractor performance, financing and site-specific challenges require intervention.

“All six road projects in the schedule are behind their planned construction progress. The delivery programme requires intervention on contractor performance, financing and site-specific constraints,” the report states. The worst-performing project in terms of the gap between actual and planned progress is the Mmokolodi Access Road, which should have been completed by the reporting date but stands at a mere 46% completion. The Radisele–Pilikwe road is another major cause for concern, with construction progress standing at just 30% against a planned 79%.

The Thamaga–Kubung road, which should have been almost complete at 98%, has reached only 61%, while the Moshupa–Manyana road stands at 42% against an anticipated 79%. On the other hand, the controversial New Xade Junction–New Xade road project has also fallen behind schedule, recording 54% completion against a planned 72%. Meanwhile, the Borobadilepe–Hebron–Mokatako road has reached 40% completion against a planned 50%. The figures paint a troubling picture of an infrastructure development programme struggling to keep pace with its own delivery schedules, despite government’s emphasis on accelerating project implementation. These delays also raise uncomfortable questions about the effectiveness of contractor selection, project supervision, financial management and accountability in the delivery of public infrastructure.

The revelation comes at a particularly difficult time for Botswana as government grapples with fiscal pressures occasioned by the downturn in the diamond industry.

Observers in the sector have indicated that prolonged construction periods could expose government to additional costs, potentially placing further pressure on already strained public finances.

But the report acknowledges the importance of infrastructure in supporting the country’s economic transformation ambitions. “Roads, water schemes, electricity connections and public buildings are essential to economic activity and the delivery of public services,” it states.

Beyond the six construction projects, government is also grappling with the maintenance of the country’s existing road network. According to the report, 15 road maintenance projects are underway, averaging 67% implementation, with completion dates stretching into December 2027. Government has also approved P772.4 million for urgent maintenance of six targeted sections of the A1 Road, one of Botswana’s most important transport corridors.

“A feasibility study for reconstruction/upgrading under a PPP was scheduled for completion by December 2026,” the report states. The proposed public-private partnership (PPP) comes as government explores alternative financing mechanisms for infrastructure development.

However, the persistent delays in ongoing construction projects raise questions about government’s capacity to deliver new infrastructure commitments while completing existing ones. In its assessment of implementation pressures, the report acknowledges that government is addressing delivery schedules across the road programme. “Careful management of public finances remains essential as the country develops additional sources of growth and revenue,” the report states.

For communities awaiting the completion of the affected roads, the delays prolong difficulties in accessing markets, healthcare facilities, schools and other essential services. Critics further argue that for Boko’s administration, which has placed infrastructure development at the heart of its national transformation agenda, the poor performance of the six projects presents a significant test of its ability to move from promises to delivery.