Two decades of thirst, another promise for Molepolole

Thirsty Village of Molepolole . PIC MORERI SEJAKGOMO
 
Thirsty Village of Molepolole . PIC MORERI SEJAKGOMO

Now, President Duma Boko has added another chapter to the long-running water crisis, announcing a new financing arrangement that raises fresh hopes. In his State of the Nation Address (SONA) on Monday, Boko acknowledged the suffering of residents of Botswana's largest village. He announced that the Molepolole–Thamaga Water Network Project has been selected for financing under a Standard Chartered Bank facility backed by the Multilateral Investment Guarantee Agency (MIGA). The populous Kweneng district capital has watched successive governments announce multimillion-pula projects, postpone construction and blame financial constraints. The latest announcement represents another significant moment in a struggle stretching across different political administrations. However, Boko did not disclose the amount secured for the project, when construction would commence, when the financing would be finalised or, most importantly, when Bakwena can expect uninterrupted water supply.

'To cite an example Mr. Speaker, Molepolole, Botswana’s largest village, has endured nearly two decades of unreliable water supply,' Boko told Parliament. “We have therefore prioritised this long-standing challenge, and the Molepolole-Thamaga Water Network Project has been selected for financing under the Standard Chartered Bank MIGA-backed facility, paving the way for a lasting solution to water security in the area.' The announcement is significant, particularly because Boko has publicly acknowledged a crisis that has frustrated generations of residents and survived numerous government interventions. For Molepolole, the problem has never been shortage of promises but rather, the slow conversion of the promises into reliable services. A crisis that outlived governments The history of Molepolole's water crisis reads like a catalogue of public frustration, expensive infrastructure interventions and repeatedly missed expectations. As far back as January 2018, residents had become so frustrated that they organised themselves under the banner of the 'Give us water campaign Molepolole', mobilising through WhatsApp and Facebook before convening a public meeting.

The campaign brought together villagers who believed their appeals had fallen on deaf ears. They described the situation as intolerable and urged residents to collectively demand answers from government. 'We are faced with a crisis and we know the situation much better, let us come up with ways to resolve the trouble. We are not here to cause any riots we want the country’s leadership to hear our appeal,' organisers said at the time. Their remarks captured a community that had grown tired of living without a basic necessity despite having household water connections. Other residents described pushing wheelbarrows over long distances to collect water, relying on overwhelmed communal tanks and travelling as far as Thamaga in search of supplies. Some complained that opportunistic traders were selling 20-litre buckets of water. Eight years later, Boko's acknowledgement that Molepolole has endured nearly two decades of unreliable water supply demonstrates how deeply entrenched the problem has become.

What was already described as a crisis many years ago still remains an issue of national importance in 2026. The history of government interventions also raises questions about how much public funds has been committed to resolving the crisis and why the problem persists. In 2023, the then Botswana Democratic Party (BDP) government had postponed the Molepolole Water and Sanitation Project after failing to secure sufficient funding. The project, initially expected to commence during the 2020-2021 financial year, had been estimated at P2.5 billion, with an anticipated implementation period of 18 months. However, financial constraints prevented construction from proceeding as originally envisaged. Then Minister of Lands and Water Affairs, Kefentse Mzwinila, informed Parliament that the project had been included in the Transitional National Development Plan, with an allocation of P1.9 billion, including P416.7 million for the 2023-2024 financial year. Government subsequently divided the undertaking into six contracts, hoping that simultaneous implementation would accelerate delivery and reduce disruption. But the funding difficulties persisted and by November 2024, shortly after the Umbrella for Democratic Change (UDC) assumed power, the new administration was confronting essentially the same challenge.

Minister of Water and Human Settlement, Onneetse Ramogapi, revealed in Parliament that Molepolole required approximately 13 million litres of water daily. Surprisingly, he explained that the village's water demand was being met at supply level, but its deteriorating distribution infrastructure prevented residents from receiving reliable water supply. The network had exceeded its designed lifespan by more than a decade, resulting in water losses of up to 46%. This revelation exposed a fundamental problem and that Molepolole's water crisis was not simply about sourcing more water, but also about delivering it through an ageing and inefficient distribution network.

Certain wards, including Phalane, Matlhalerwa-a-Botue, Motiketsane, Mokobeng, Mokgopeetsane, Steken Hill and Sedumedi, were particularly disadvantaged because they were situated above the existing service reservoirs. Other areas, including Gantshonyana, Sesha, Motswasele and Legonono, remained unserviced. Against this background, Boko's latest announcement raises an important question about whether the proposed financing will address the entire distribution network or only selected components. When Ramogapi updated Parliament in November 2024, two of the six contracts were under implementation while four awaited funding. Contract One, valued at approximately P664 million, involved primary water infrastructure and the establishment of nine distribution zones. It commenced in September 2024, with completion originally scheduled for March 24, 2026. At the time of Ramogapi's update, physical progress stood at just six percent. Contract Six, worth approximately P608 million, involved constructing a 25.6-million-litre wastewater treatment plant. It had commenced in October 2023 and was scheduled for completion by August 30, 2025. Its reported progress in November 2024 stood at 41%.

The remaining contracts, covering extensive water reticulation and sewerage infrastructure, were being delayed by insufficient funding. Now, with the original completion dates for Contracts One and Six already past, Boko's SONA leaves another critical issue unresolved. The President's address did not provide details of whether those past projects were completed within their revised schedules, and their present operational status. UDC's political test Beyond engineering and financing, the water crisis carries considerable political significance. When the UDC swept into power in October 2024, Molepolole residents were amongst those expecting a change in the government's approach to longstanding service delivery problems. The party captured both Molepolole North and Molepolole South parliamentary constituencies, represented by Arafat Khan and Shima Monageng respectively.

During the campaign, both politicians identified water shortages as a priority requiring urgent intervention. Following his election, Monageng pledged to work towards ending the crisis. 'I have interest to see Molepolole transform and the water shortage being a thing of the past. This is a test for us and we have to hit the ground running in seeing what has been the issue and how we can address the situation,' he said. Khan similarly promised to pursue solutions to the village's unreliable supply. However, the frustrations did not disappear with the change of government and in February 2025, Khan openly criticised the continued neglect of Molepolole's infrastructure needs. He questioned why Bakwena had endured such difficulties despite decades of parliamentary representation. 'What wrong have we done as Bakwena? All our former MPs Daniel Kwelagobe and Mohammed Khan have spoken about water, sewage, and roads. Why has the Bakwena community been left behind?' the disappointed MP asked in Parliament. Khan indicated that approximately P1.5 billion was required to complete two critical water projects, Contracts Two and Four. His intervention highlighted the financial challenges confronting the new administration and the growing pressure on elected representatives to deliver tangible improvements.

More recently, during the 2026 Budget Speech debate, Monageng expressed optimism that the Molepolole Water Supply and Distribution Pipeline Project would finally provide relief. But he also emphasised that infrastructure projects must be completed on time and within their approved budgets. His warning is particularly relevant given Molepolole's history of delayed project implementation. The BDP administration faced years of criticism over its inability to resolve Molepolole's water crisis. The UDC inherited the problem in 2024 and has since made its own commitments to deliver a lasting solution. For residents who have spent years collecting water in buckets, depending on communal tanks and enduring unpredictable supplies, Boko's announcement offers a potentially important breakthrough.