Race Against Time To Complete NWTG

BPC Transmission line 2. PIC: MORERI SEJAKGOMO
BPC Transmission line 2. PIC: MORERI SEJAKGOMO

The Botswana Power Corporation (BPC) is in a race against time to reach set targets, but seems to be falling short of meeting the goal to finish the North West Transmission Grid Commission (NWTGC) project on schedule.

The NWTGC project’s progress as at July 2019 was at 73% against the targeted 86%.

However, Project Services manager, George Moeti there has revealed recovery plans in place to catch up on lost time.

Editor's Comment
Congratulations Anicia Gaothuse!

The contest had 10 beautiful young girls as finalists and unfortunately only one could wear the crown.The judges picked Anicia Gaothuse. To all those who feel their contestant should have won ahead of Anicia for whatever reason, hardly; the judges found Anicia to be the best among the best, so desist from disrespecting our newly crowned queen on social media or anywhere else, for that matter! Each of the 10 beautiful young women had supporters...

Have a Story? Send Us a tip
arrow up