Khato cut cost of multimillion pula project

Critics blame the contractor for the ballooning of the project's budget
Critics blame the contractor for the ballooning of the project's budget

Documents perused by Mmegi have revealed that contrary to perceptions that the winning bidder, Khato Civils were responsible for the P900 million project cost hike that was recently put before Cabinet, and later surfaced in Parliament, the amount of cost estimates was done by the parent Ministry and Water Utilities Corporation’ (WUC).

It was also tabled before Cabinet way before the tender award was announced, the documents revealed.

The documents also established that when the award of the tender was announced, Khato’s winning bid was put at P781 million or USD 65 million, while the Ministry’s own project estimate later surfaced to be P900 million. Critics questioned the price hike and blamed the contractor for the ballooning of the project budget.

Editor's Comment
Routine child vaccination imperative

The recent Vaccination Day in Motokwe, orchestrated through collaborative efforts between UNICEF, USAID, BRCS, and the Ministry of Health, underscores a commendable stride towards fortifying child health services.The painful reality as reflected by the Ministry of Health's data regarding the decline in routine immunisation coverage since the onset of the pandemic, is a cause for concern.It underscores the urgent need to address the...

Have a Story? Send Us a tip
arrow up