Marubeni, Posco up the ante in push for P8bn deal

Yokota says a deal is on the horizon PIC: MORERI SEJAKGOMO
Yokota says a deal is on the horizon PIC: MORERI SEJAKGOMO

Marubeni Corp and Posco Energy have redoubled their efforts to seal the P8 billion project to expand Morupule B, with the launch of a local office and high-level engagement with the new government administration.

The two Asian mega-corps – Marubeni from Japan and Posco from South Korea – won the tender to expand Morupule B by 300MW in 2015 and were due to have begun work last January. Morupule B currently has four units capable of producing 600MW and the new project would have added two more.

However, a dispute with government over guarantees and other commitments for the project has meant a prolonged delay and government has threatened to put the project on the back-burner arguing that the country was being asked to shoulder an unfair proportion of risk for the project.

Editor's Comment
Inspect the voters' roll!

The recent disclosure by the IEC that 2,513 registrations have been turned down due to various irregularities should prompt all Batswana to meticulously review the voters' rolls and address concerns about rejected registrations.The disparities flagged by the IEC are troubling and emphasise the significance of rigorous voter registration processes.Out of the rejected registrations, 29 individuals were disqualified due to non-existent Omang...

Have a Story? Send Us a tip
arrow up