North-West grid extension to create 8,000 jobs
Tuesday, January 23, 2018
Speaking in Shakawe yesterday morning at the launch of the North-West Transmission Grid (NWTG) project, Botswana Power Corporation CEO, Stefan Schwarzfischer said jobs created would come from new entities starting up and existing ones expanding.
The first phase of the project is to run from January 2018 to December 2019, will involve 500-kilometre transmission lines and substations running from the 600MW Morupule B Power Station to Maun.
The recent disclosure by the IEC that 2,513 registrations have been turned down due to various irregularities should prompt all Batswana to meticulously review the voters' rolls and address concerns about rejected registrations.The disparities flagged by the IEC are troubling and emphasise the significance of rigorous voter registration processes.Out of the rejected registrations, 29 individuals were disqualified due to non-existent Omang...