Glass project under-budgeted by P800million
Tuesday, August 18, 2015
This is P800 million more than the projected cost of the project when it commenced in 2008. The project was a joint venture between Botswana Development Corporation and Fengyue China.
Two years after it was liquidated, sources close to the project have confided in Mmegi that the BDC has in fact spent approximately P700 million and has given up on pursuing it. Initially, the corporation said it had spent only P400million.
The recent disclosure by the IEC that 2,513 registrations have been turned down due to various irregularities should prompt all Batswana to meticulously review the voters' rolls and address concerns about rejected registrations.The disparities flagged by the IEC are troubling and emphasise the significance of rigorous voter registration processes.Out of the rejected registrations, 29 individuals were disqualified due to non-existent Omang...