F/town-Tonota Road a tad behind schedule � engineer

Chief Roads Engineer North East Letlhogela Raditapa. PIC KEOAGILE BONANG
Chief Roads Engineer North East Letlhogela Raditapa. PIC KEOAGILE BONANG

FRANCISTOWN: The Francistown-Tonota road, which is currently being upgraded, is behind time by slightly over four percent. So far work on the road is at 63.8% though it was supposed to be at 67.5 % at this stage.

The Chief Roads Engineer at the Department of Roads in the North East region Letlhogela Radipata made the disclosure when addressing participants at a stakeholder seminar in Francistown yesterday.

The seminar was organised to brief the business community about the closure of some parts of the Francistown-Tonota road to pave way for the construction and upgrading of the road by the contractor China Railways Seventh Group. “Relocation of services such as electricity cables, water conveying pipes and telephone cables to pave way for construction of the road are some of the major reasons for the delay.

Editor's Comment
Inspect the voters' roll!

The recent disclosure by the IEC that 2,513 registrations have been turned down due to various irregularities should prompt all Batswana to meticulously review the voters' rolls and address concerns about rejected registrations.The disparities flagged by the IEC are troubling and emphasise the significance of rigorous voter registration processes.Out of the rejected registrations, 29 individuals were disqualified due to non-existent Omang...

Have a Story? Send Us a tip
arrow up