Last Updated
Wednesday 29 July 2015, 18:00 pm.
World Bank forces Morupule B investigation

The government has cut a P14 million deal with two international firms to provide technical and legal prop-ups at Morupule B Power Station.
By Staff Writer Thu 30 Jul 2015, 12:07 pm (GMT +2)
Mmegi Online :: World Bank forces Morupule B investigation








The Minister of Minerals, Energy and Water Resources, Kitso Mokaila, told Parliament this week that Aurecon AME Limited and Norton Rose have been contracted following a number of delays, boiler failures and questions on the technical integrity of the plant.

Mokaila said the government and the World Bank agreed that Aurecon should undertake a quick two-week audit of the plant with Norton Rose providing legal advice to address contractual matters on operation and maintenance."Following the Morupule B power plant's audit by Aurecon, which has revealed that there were no fundamental design flaws that could frustrate operation, Norton Rose and Aurecon will be engaged for a seven-month period at an estimated cost of P14.8 million to strengthen the BPC project management oversight," Mokaila said.

He told MPs that the engagement of Aurecon and Norton Rose is just a tactical intervention meant to ensure a firmer project oversight and timely delivery to address the current power crisis in the country. He stated that bringing Aurecon on board would go a long way to reduce government's liquidated damages. In the long term, he added, the BPC board, in consultation with the ministry, has seen the need for the engagement of a reputable international firm to manage BPC on a two-year compact.

This is why the BPC board is in discussions with the Electricity Supply Board International (Pty) Ltd. Mokaila said the original timeline for completion of Morupule B was October 2012. The target dates were not met for various reasons, such as a 2011 truckers' strike in South Africa that delayed movement of equipment from Durban to the site. There was also bad weather in 2010-2012 and problems encountered

during commissioning, such as blockages and steam tube leaks on Boiler One and Two respectively.

"The contractor's non-compliance with the Safety, Health and Environmental (SHE) standards in 2012 did also contribute to the delays and the key one being boiler failures, technical integrity and non-compliance with SHE standards which resulted in three fatalities," Mokaila said.

The project was behind schedule, with telling effects on BPC finances as commissioning of the first unit is more than 12 months behind schedule, which puts the technical integrity of the plant in doubt.The minister said in response to the non-conformance, BPC has undertaken various actions to improve safety on site. These include suspending all work at height activities, increasing site verifications, checks on the number of security personnel, appointing a specialised third party firm to erect safe scaffolding and appointing a professional firm to assist in implementation of the SHE plan.

The minister said he was aware that the telling effects brought about by the inordinate delay in bringing the power plant into service have been severe as seen in widespread load shedding across the country. "The problems have been identified and remedial action is being taken, including strengthening the BPC project management staff. I am in continual communication with my South African counterparts on these challenges and their response has been reassuring and positive," Mokaila explained.

He said he has met the CEO of the contractor, China National Electric Equipment Corporation (CNEEC) and Fitchner, the  engineers, to express concern on the failure to deliver the plant in time. The minister asserted that he is focused on bringing the power station into service as soon as July 2013.



Exchange Rates
FOREIGN EXCHANGE: Thursday, 30 Jul 2015
FOREIGN / PULA
PULA / FOREIGN
1 USD = Pula   10.1010
1 GBP = Pula   15.7480
1 EUR = Pula   11.0619
1 YEN = Pula   0.0813
1 ZAR = Pula   0.8007
1 Pula = USD   0.099
1 Pula = GBP   0.0635
1 Pula = EUR   0.0904
1 Pula = YEN   12.3
1 Pula = ZAR   1.2489
Stock Exchange
STOCK EXCHANGE: Wednesday, 29 Jul 2015
DOMESTIC STOCKS
BARCLAYS
434
BIHL
1415
CHOBE
600
CHOPPIES
490
CRESTA
100
ENGEN
817
FNBB
392
FSG
260
FURNMART
159
G4S
349
LETLOLE
222
LETSHEGO
329
NAP
242
OLYMPIA
20
PRIMETIME
286
RDCP
230
SECHABA
2850
SEFALANA
1251
STANCHART
1270
TURNSTAR
275
WIL
475
IMARA
274
have a story? Send us a Tip
  • Previous
    Pixels Poster
    Next
    Masa Centre
    ::: Friday 24 Jul - Thursday 30 Jul :::
    Pixels
    Entourage
    Black Sea
    Cut Bank
    Minions
  • Previous
    Minions Poster
    Next
    Riverwalk
    ::: Friday 24 Jul - Thursday 30 Jul :::
    Minions
    Terminator Genisys
    Entourage
    Pixels
  • Previous
    Pixels Poster
    Next
    Gamecity
    ::: Friday 24 Jul - Thursday 30 Jul :::
    Pixels
    Entourage
    Minions
    Terminator Genisys
    Magic Mike XXL
    Ted 2
Selefu
Death of BPP